How to cite this paper
Rashid, Y. (2020). Analysis of delay factors and their effects on construction projects.Management Science Letters , 10(6), 1197-1204.
Refrences
Acharya, N. K., Dai Lee, Y., & Man Im, H. (2006). Conflicting factors in construction projects: Korean perspective. Engi-neering, Construction and Architectural Management, 13(6), 543-566.
Aibinu, A. A., & Jagboro, G. O. (2002). The effects of construction delays on project delivery in Nigerian construction in-dustry. International journal of project management, 20(8), 593-599.
Al-Khalil, M. I., & Al-Ghafly, M. A. (1999). Delay in public utility projects in Saudi Arabia. International Journal of Pro-ject Management, 17(2), 101-106.
Al‐Kharashi, A., & Skitmore, M. (2009). Causes of delays in Saudi Arabian public sector construction projects. Construc-tion Management and Economics, 27(1), 3-23.
Arditi, D., & Pattanakitchamroon, T. (2006). Selecting a delay analysis method in resolving construction claims. Interna-tional Journal of Project Management, 24(2), 145-155.
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Man-agement, 24(4), 349-357.
Baldwin, J. R., Manthei, J. M., Rothbart, H., & Harris, R. B. (1971). Causes of delay in the construction industry. Journal of the Construction Division, 97(2), 177-187.
Browne, M. W., & Cudeck, R. (1993). Alternative ways of assessing model fit. Sage focus editions, 154, 136-136.
Chou, J. S., & Yang, J. G. (2012). Project management knowledge and effects on construction project outcomes: An em-pirical study. Project Management Journal, 43(5), 47-67.
Deng, X., Pheng, L. S., & Zhao, X. (2014). Project system vulnerability to political risks in international construction pro-jects: the case of Chinese contractors. Project Management Journal, 45(2), 20-33.
Doloi, H. (2012). Cost overruns and failure in project management: Understanding the roles of key stakeholders in con-struction projects. Journal of Construction Engineering and Management, 139(3), 267-279.
Eastman, C. M. (2018). Building product models: computer environments, supporting design and construction. CRC press.
Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M. (2008). Causes of delay in building construction projects in Egypt. Journal of Construction Engineering and Management, 134(11), 831-841.
Haseeb, M., Bibi, A., & Rabbani, W. (2011). Problems of projects and effects of delays in the construction industry of Pa-kistan. Australian Journal of Business and Management Research, 1(5), 41-50.
Jaafari, A. (2001). Management of risks, uncertainties and opportunities on projects: time for a fundamental shift. Inter-national Journal of Project Management, 19(2), 89-101.
Lo, T. Y., Fung, I. W., & Tung, K. C. (2006). Construction delays in Hong Kong civil engineering projects. Journal of Construction Engineering and Management, 132(6), 636-649.
Maqbool, R., Sudong, Y., Manzoor, N., & Rashid, Y. (2017). The impact of emotional intelligence, project managers’ competencies, and transformational leadership on project success: An empirical perspective. Project Management Journal, 48(3), 58-75.
Maqbool, R., Rashid, Y., Sultana, S., & Sudong, Y. (2018). Identifying the critical success factors and their relevant as-pects for renewable energy projects; an empirical perspective. Journal of Civil Engineering and Management, 24(3), 223-237.
Marsh, H. W., & Hocevar, D. (1985). Application of confirmatory factor analysis to the study of self-concept: First-and higher order factor models and their invariance across groups. Psychological Bulletin, 97(3), 562.
Mohamed, N., Ridwan, A., Saoula, O., & Issa, M. (2019). Factors causing mismanagement in public/private contracts: An Indonesian perspective. Management Science Letters, 9(9), 1429-1438.
Nilashi, M., Zakaria, R., Ibrahim, O., Majid, M. Z. A., Zin, R. M., & Farahmand, M. (2015). MCPCM: a DEMATEL-ANP-based multi-criteria decision-making approach to evaluate the critical success factors in construction projects. Arabian Journal for Science and Engineering, 40(2), 343-361.
Neter, J., Wasserman, W., & Kutner, M. H. (1989). Applied linear regression models.
Odeh, A. M., & Battaineh, H. T. (2002). Causes of construction delay: traditional contracts. International Journal of Pro-ject Management, 20(1), 67-73.
Rahsid, Y., Haq, S., & Aslam, M. (2013). Causes of delay in construction projects of Punjab-Pakistan: An empirical study. Journal of Basic and Applied Scientific Research, 3(10), 87-96.
Rashid, M. R. (2017). Detrimental changes and construction projects: need for comprehensive controls.
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project management, 25(5), 517-526.
Shaikh, A. W., Muree, M. R., & Soomro, A. S. (2010). Identification of critical delay factors in construction. Sindh Uni-versity Research Journal-SURJ (Science Series), 42(2).
Shehu, Z., Endut, I. R., Akintoye, A., & Holt, G. D. (2014). Cost overrun in the Malaysian construction industry projects: A deeper insight. International Journal of Project Management, 32(8), 1471-1480.
Sweis, G., Sweis, R., Hammad, A. A., & Shboul, A. (2008). Delays in construction projects: The case of Jordan. Interna-tional Journal of Project Management, 26(6), 665-674.
Tam, C. M., Zeng, S. X., & Deng, Z. M. (2004). Identifying elements of poor construction safety management in China. Safety science, 42(7), 569-586.
Wang, J., Sun, W., Shou, W., Wang, X., Wu, C., Chong, H. Y., ... & Sun, C. (2015). Integrating BIM and LiDAR for real-time construction quality control. Journal of Intelligent & Robotic Systems, 79(3-4), 417-432.
Wei, K. S. (2010). Causes, effects and methods of minimizing delays in construction projects. A project report.
Williams, T. (2003). Assessing extension of time delays on major projects. International Journal of Project Management, 21(1), 19-26.
Yang, J. B., & Wei, P. R. (2010). Causes of delay in the planning and design phases for construction projects. Journal of Architectural Engineering, 16(2), 80-83.
Zaneldin, E. K. (2006). Construction claims in United Arab Emirates: Types, causes, and frequency. International Journal of Project Management, 24(5), 453-459.
Zhu, G., Bard, J. F., & Yu, G. (2005). Disruption management for resource-constrained project scheduling. Journal of the Operational Research Society, 56(4), 365-381.
Aibinu, A. A., & Jagboro, G. O. (2002). The effects of construction delays on project delivery in Nigerian construction in-dustry. International journal of project management, 20(8), 593-599.
Al-Khalil, M. I., & Al-Ghafly, M. A. (1999). Delay in public utility projects in Saudi Arabia. International Journal of Pro-ject Management, 17(2), 101-106.
Al‐Kharashi, A., & Skitmore, M. (2009). Causes of delays in Saudi Arabian public sector construction projects. Construc-tion Management and Economics, 27(1), 3-23.
Arditi, D., & Pattanakitchamroon, T. (2006). Selecting a delay analysis method in resolving construction claims. Interna-tional Journal of Project Management, 24(2), 145-155.
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Man-agement, 24(4), 349-357.
Baldwin, J. R., Manthei, J. M., Rothbart, H., & Harris, R. B. (1971). Causes of delay in the construction industry. Journal of the Construction Division, 97(2), 177-187.
Browne, M. W., & Cudeck, R. (1993). Alternative ways of assessing model fit. Sage focus editions, 154, 136-136.
Chou, J. S., & Yang, J. G. (2012). Project management knowledge and effects on construction project outcomes: An em-pirical study. Project Management Journal, 43(5), 47-67.
Deng, X., Pheng, L. S., & Zhao, X. (2014). Project system vulnerability to political risks in international construction pro-jects: the case of Chinese contractors. Project Management Journal, 45(2), 20-33.
Doloi, H. (2012). Cost overruns and failure in project management: Understanding the roles of key stakeholders in con-struction projects. Journal of Construction Engineering and Management, 139(3), 267-279.
Eastman, C. M. (2018). Building product models: computer environments, supporting design and construction. CRC press.
Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M. (2008). Causes of delay in building construction projects in Egypt. Journal of Construction Engineering and Management, 134(11), 831-841.
Haseeb, M., Bibi, A., & Rabbani, W. (2011). Problems of projects and effects of delays in the construction industry of Pa-kistan. Australian Journal of Business and Management Research, 1(5), 41-50.
Jaafari, A. (2001). Management of risks, uncertainties and opportunities on projects: time for a fundamental shift. Inter-national Journal of Project Management, 19(2), 89-101.
Lo, T. Y., Fung, I. W., & Tung, K. C. (2006). Construction delays in Hong Kong civil engineering projects. Journal of Construction Engineering and Management, 132(6), 636-649.
Maqbool, R., Sudong, Y., Manzoor, N., & Rashid, Y. (2017). The impact of emotional intelligence, project managers’ competencies, and transformational leadership on project success: An empirical perspective. Project Management Journal, 48(3), 58-75.
Maqbool, R., Rashid, Y., Sultana, S., & Sudong, Y. (2018). Identifying the critical success factors and their relevant as-pects for renewable energy projects; an empirical perspective. Journal of Civil Engineering and Management, 24(3), 223-237.
Marsh, H. W., & Hocevar, D. (1985). Application of confirmatory factor analysis to the study of self-concept: First-and higher order factor models and their invariance across groups. Psychological Bulletin, 97(3), 562.
Mohamed, N., Ridwan, A., Saoula, O., & Issa, M. (2019). Factors causing mismanagement in public/private contracts: An Indonesian perspective. Management Science Letters, 9(9), 1429-1438.
Nilashi, M., Zakaria, R., Ibrahim, O., Majid, M. Z. A., Zin, R. M., & Farahmand, M. (2015). MCPCM: a DEMATEL-ANP-based multi-criteria decision-making approach to evaluate the critical success factors in construction projects. Arabian Journal for Science and Engineering, 40(2), 343-361.
Neter, J., Wasserman, W., & Kutner, M. H. (1989). Applied linear regression models.
Odeh, A. M., & Battaineh, H. T. (2002). Causes of construction delay: traditional contracts. International Journal of Pro-ject Management, 20(1), 67-73.
Rahsid, Y., Haq, S., & Aslam, M. (2013). Causes of delay in construction projects of Punjab-Pakistan: An empirical study. Journal of Basic and Applied Scientific Research, 3(10), 87-96.
Rashid, M. R. (2017). Detrimental changes and construction projects: need for comprehensive controls.
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project management, 25(5), 517-526.
Shaikh, A. W., Muree, M. R., & Soomro, A. S. (2010). Identification of critical delay factors in construction. Sindh Uni-versity Research Journal-SURJ (Science Series), 42(2).
Shehu, Z., Endut, I. R., Akintoye, A., & Holt, G. D. (2014). Cost overrun in the Malaysian construction industry projects: A deeper insight. International Journal of Project Management, 32(8), 1471-1480.
Sweis, G., Sweis, R., Hammad, A. A., & Shboul, A. (2008). Delays in construction projects: The case of Jordan. Interna-tional Journal of Project Management, 26(6), 665-674.
Tam, C. M., Zeng, S. X., & Deng, Z. M. (2004). Identifying elements of poor construction safety management in China. Safety science, 42(7), 569-586.
Wang, J., Sun, W., Shou, W., Wang, X., Wu, C., Chong, H. Y., ... & Sun, C. (2015). Integrating BIM and LiDAR for real-time construction quality control. Journal of Intelligent & Robotic Systems, 79(3-4), 417-432.
Wei, K. S. (2010). Causes, effects and methods of minimizing delays in construction projects. A project report.
Williams, T. (2003). Assessing extension of time delays on major projects. International Journal of Project Management, 21(1), 19-26.
Yang, J. B., & Wei, P. R. (2010). Causes of delay in the planning and design phases for construction projects. Journal of Architectural Engineering, 16(2), 80-83.
Zaneldin, E. K. (2006). Construction claims in United Arab Emirates: Types, causes, and frequency. International Journal of Project Management, 24(5), 453-459.
Zhu, G., Bard, J. F., & Yu, G. (2005). Disruption management for resource-constrained project scheduling. Journal of the Operational Research Society, 56(4), 365-381.